Spackenkill School District, NY

Project Size: $2.9 Million
Cash Flow: $1.2 Million
Total Value: $4.1 Million
Completion Date: May 2015
Project Description:
Energy Performance Contract

.................................................
Annual Energy Savings: $170,724
Reduction in Energy Costs: 38.0%

.................................................

Project Description
Although Spackenkill UFSD had already retained the services of an energy consultant that focused on changing staff behavior to reduce costs, administrators still desired a means through which they could make systemic infrastructure upgrades to ensure their equipment was functioning efficiently and effectively. ECG was brought in to design and manage an energy performance contract that will do just that. The scope of the EPC includes the replacement of many items that cannot be controlled through behavioral changes, such as extensive energy management system improvements and a boiler replacement.

Project Highlights

  • lighting upgrades
  • exterior lighting upgrades
  • lighting controls - occupancy sensors
  • energy management system upgrades
  • demand control ventilation
  • new motors
  • electronic machine management
  • computer power management
  • building envelope improvements
  • boiler controls/burners
  • boiler replacement
  • domestic hot water system upgrades
  • steam system upgrades
  • pipe insulation
  • photovoltaic (solar) panels
  • destratification fans
  • vending machine controllers
  • walk-in freezer and cooler controllers